Enhancing irrigation infrastructure ensures resilient and efficient water management, improving agricultural productivity and sustainability. Through modernized canal systems, slope protection, and advanced drainage solutions, we secure water resources for communities and future generations.
The Slope Protection Works, Canal Lining, Structures, Terminal Facilities, and Access Road construction is 94% complete in Claveria, Cagayan as of February 6, 2025. Ongoing activity includes formworks for the drainage canal vertical wall at Nagsabaran Drainage Canal.
Funded under Climate Change Adaptation Works (CCAW), the project (Contract No. NCB-RO2-CB17-24) is implemented by R.D. Interior Junior Construction.